Net congestion in Almere
On this page, you will find more information on net congestion in Almere regarding business establishment.
Important info
What is net congestion?
Grid congestion means that there is not enough space on the electricity grid to carry all the power. This can cause problems with new connections or the use of electricity.
On 17 November 2022, TenneT, the operator of the national high-voltage grid, announced that there is grid congestion in the Flevopolder region, including Almere. This means that the grid is too full to accommodate all desired connections. Grid congestion had previously been declared for the return supply of sustainably generated electricity, such as from solar panels, in September 2021.
New rules for electricity connections: public interest takes precedence. The network operator will then consider the purpose for which the connection is used, rather than its size (low or high consumption). Connections of public interest are given priority. The date of application is also taken into account.
Procedure as of 1 July 2026
The new prioritisation framework has 3 priority categories. In times of grid congestion, available capacity is allocated to new applications in order of the prioritisation framework. Should any power remain after allocation to the priority categories, other applicants will have their turn. The categories have been determined based on social function rather than the size of the requested connection. The following list outlines the categories. The full table is shown on the Government Gazette website.
- Category 1 Congestion Mitigator: electricity generation and storage.
- Category 2 Safety: acute healthcare, industry for highly sensitive technologies, drinking water supply, defence, police, fire brigade, sewerage.
- Category 3 Basic needs: housing, waste collection, education (up to MBO), public transport, heat supply.
The grid operators have indicated that applications for large consumers in terms of function want to claim priority can indicate this with immediate effect and thereby get clarity about their connection earlier than 1 July. Read more about social prioritisation on the Liander page.
Long delivery times for connections
Even when a connection is approved, it can take a long time to materialise. Due to a shortage of staff and materials, the waiting time can be up to two years. Find out more on Liander's website.
Network congestion scheme
July 2026 – The issue of grid congestion in the municipality of Almere affects customers who have registered or applied, or are yet to apply, for a plot for (social) facilities or for a plot on one of the business parks in Almere, and who have not applied to the network operator for an electricity connection by 17 November 2022. There is a high probability that, due to the grid congestion issue, applicants whose activities are not designated as priority cases will only be eligible for a connection after 2033–2035 (see here).
This has implications for the issue of business plots and (social) facilities as the intended use is not possible until the grid congestion issue is resolved. The municipality of Almere is taking a number of measures with immediate effect.
For business plots and (social) facilities for which the municipality has already entered into a reservation agreement or has already selected a party, provision will be made for an extension of the reservation period until the grid congestion issue for the relevant building plot (or the power issue is otherwise resolved). Due to the uncertainty of those issues, provision will also be made for an ultimate date, to be determined by the municipality, on which the reservation agreement can be terminated, should the grid congestion issue (or the power issue otherwise) still not be resolved by then. The (extended) reservation period and other conditions are subject to the prevailing land price policy.
In new selection procedures (as of this publication), the reservation period will apply until such time as the grid congestion issue for the relevant building plot (or the power issue otherwise) is resolved (including a date to be determined by the municipality for termination of the reservation agreement).
In all cases, the buyer remains responsible for the connection to the power grid and other utilities. The Municipality of Almere is not responsible for the provision of power and other utilities (except sewerage) on building plots.
Useful links
See also Transport capacity Flevoland | Liander
Also read the Q&A Liander outcomes Tennet congestion survey FGU